Rowan Street is now open to all traffic.Minor works on the shared user bridge are ongoing; it is due to open from Monday 18 May 2026.
The Rural City of Wangaratta engaged Gordon Gibson Nominees Pty Ltd for the reconstruction of Wareena Park Oval, Swan Street Wangaratta.
The reconstruction works included improved drainage and a new automatic irrigation system. Works also included new infrastructure, including perimeter fence, AFL posts, synthetic cricket pitch, coach’s boxes and concrete pads. This need was identified in the development of the 2020 Wareena Park Masterplan. The funding for this project of $600,000 has been provided by the Regional Community Sports Infrastructure Fund.
The works which began in October 2024 are now complete. Wareena Park Oval was reopened to the public on Friday 18 July 2025.
Works program:
July 2025 - Due to wet weather, landscaping on the southern end of the ground remains incomplete. Visitors are advised to exercise caution around mounded dirt and muddy areas.
Photos taken in early May 2025:
Photo below taken 1 April 2025:
Progress Photos as of 14 November 2024:
Stripping of the existing surface and preparation for the sub formation of new drainage.
Gordon Gibson using local contractors Cooks Earthmoving & Laser Landforming Pty Ltd in preparation for the new oval formation.