Redcamp Bridge Replacement - Boggy Creek Myrrhee
- Completion Date22 April 2025
Redcamp Bridge over Boggy Creek has been replaced after a contract was awarded to Waratah Constructions Pty Ltd. The deck of the bridge was strengthened to increase its capacity to T44. The deck overlay has been removed and new deck slab with additional structural steel beams along with double layer guard rails has been constructed for strengthening purpose.
Funding for this project has been provided by the Bridges Renewal Program (BRP), the Heavy Vehicle Safety and Productivity Program (HVSPP) and the Heavy Vehicle Rest Area initiative (HVRA).
The bridge was fully closed to all traffic from 31 March - 22 April 2025, to allow the contractor to remove the deck (the surface on top of bridge that vehicles drive on) and install the new bridge deck.
Works commenced on 21 October 2025 and were completed early May 2025.
Thank you to the local community for your patience while we made these important upgrades.







7 April 2025 - Steel Studs being welded to Beams


Bridge completed early May 2025



