Skip to content Skip to navigation

Cruse Street Extension

Council has invested $9.3m in road improvements in Wangaratta's North West growth corridor.

Project Overview

Timelines: February - late 2019 (completed September 2019)

Objective: To open up Wangaratta's North West growth corridor.

Project Details

Cruse Street Extension:

  • $7.4m contract awarded to MACA Infrastructure
  • Construct a 1.5km road from Cruse Street (entry to turf club) to Worland Road
  • Included will be a 1.5km shared path
  • The road will run adjacent to Bella Way
  • It will connect with Worland Road and Reith Road
  • A three span bridge will be built over Three Mile Creek


Intersection:

  • $1.95m contract awarded to O'Loughlin Excavations
  • Osboldstone Road and Sisely Avenue intersection will be improved
  • This will involve staggering where Osboldstone Road currently meets Sisely Avenue
Back to top